[Mesh] I need wiring status for the entrance area please...

danarauz at gmail.com danarauz at gmail.com
Mon Jun 22 08:41:59 PDT 2015


Marc,

Before I read your reply I had already confirmed with Mike about tomorrow
Tuesday, I don't want to cancel if we can still use his help and tools.
Do you feel that I should retain the appointment and work in the basement
with him instead?
Would it be useful? I am asking because I haven't observe what is going on
the basement; so I am not sure.

In addition to what you said it is pending, would be nice if someone has a
cable tester (I cannot find mine) to make sure all pairs are correctly in
place.


Daniel




On Mon, Jun 22, 2015 at 2:25 AM, Marc Juul <juul at labitat.dk> wrote:

>
>
> On Sun, Jun 21, 2015 at 10:03 PM, Lesley Bell <lbx2045 at gmail.com> wrote:
>
>> Daniel,
>>
>> Marc brought an approximately 2 foot long drill bit, but it still wasn't
>> long enough to drill all the way through.
>>
>
> I managed to make it work. The cable has been run. It was a super annoying
> run both due to the hole being problematic and because the TIL office had
> lots of little nooks and crannies and was fully of stuff that needed moving
> around.
>
> Other stuff we did today:
>
> Bought more CAT6 (non-shielded since that was all we could get on a
> Sunday) and female CAT6 connectors.
>
> Drilled the long hole for the basement cable but it might not quite be
> wide enough (since that cable is shielded CAT6) so we will probably need a
> slightly wider diameter very long drill bit.
>
> Finished running the CCL node cable.
>
> Crimped the ends for the CCL node and the Disco Room node.
>
> Still To Do:
>
> Add female ethernet ports to each end of La Commune to Public Terminals
> cable
>
> Mount La Commune node on wall
>
> Finish running the basement cable.
>
> Mount basement node.
>
> Run a cable up over the upstairs bathroom, above the false ceiling and
> terminate at the upstairs public terminals. We will place a switch here
> which will connect to the cable going to La Commune via the TIL office.
> This should be a fairly easy run as only about 1/3 of the total run needs
> to be run nicely along a wall with cable clip nails.
>
> Test all cables and apply PoE.
>
> Configure all nodes.
>
> --
> marc/juul
>



-- 

- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - -
Help open a people-powered common space in Oakland, California!
https://omnicommons.org/donate
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - -
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://sudoroom.org/lists/private/mesh/attachments/20150622/1e9e5444/attachment.html>


More information about the mesh mailing list