[forwarding to omni-building mailing list]
So does this mean that Sudo can't complete it's electrical upgrades until
CCL does theirs, for example?
Patrik
On Fri, Aug 29, 2014 at 4:42 PM, Whitney Lawrence <whitneyel3(a)gmail.com>
wrote:
All,
Having discussed the permit process at length with David and Hol, we
came to the conclusion that coordinating our efforts makes the most sense.
This will save permitting costs and not aggravate the inspector, who
otherwise will need to plan a visit for every piece-wise permit. Electrical
plans should be documented to all extent possible. This means drawings of
what is to be removed and what will need to be installed. The drawings are
not any consequence to the city nor inspector, however, they are very
useful for in-house coordination and contractor bid process.
The permit should be comprised of generalities that describe the minor
changes to the existing electrical system. Furthermore, it should be for
the *entire* building. Inspection is required prior to electrifying
any new or modified circuits. The inspector will plan on coming one time to
inspect everything, plugs need to be out of their boxes, jbox's exposed w/o
the plate cover (but the cover needs to be present), new breakers should
not be installed in sub-panels unless the entire panel is locked and tagged
out (this means no one can accidentally turn on the supply breaker).
Lastly, we need to have a licensed electrician preform the install. So
go through your contacts. Lastly I think we should meet face to face to
discuss how to move forward and to review the permit draft which needs to
be prepared. I will be out of town this weekend but will be available via
phone. This
<http://www.oaklandparkfl.org/cityservices/forms/documents/ElectricalPermitApplication2012.pdf>
is
the permit. Also you may find this
<https://docs.google.com/spreadsheets/d/1Fgw5himtlmemiXReP-fG6rP-I2RoXsSP_MAZxcNUUm0/edit#gid=548047702>useful,
the information is not exactly correct but please feel free to use it for
reference- it is what we started with to get a handle of material cost and
scope of Sudo's electrical needs.
Whit
510-396-5510
On Fri, Aug 29, 2014 at 1:13 PM, <hol(a)gaskill.com> wrote:
Steve I am forwarding this thread to Whitney who
drafted our
electrical plans and has been spearheading the electrical effort, and can
probably give you a better answer on the exact permit timeline and costs.
cheers
On 2014-08-29 11:24, Steve Orth wrote:
I think that we're almost ready with our plans. Would getting them to
you by Tuesday afternoon work for you?
On Friday, August 29, 2014, <hol(a)gaskill.com> wrote:
> Hi Steve,
>
>
>
> We were planning to pull a permit for sudo room's electrical work
> which is fully planned out. There is some overhead of getting the permit
> and the inspection, which I believe is ~$160 which could be spread over the
> 2 projects. Throughout the building we are planning to address things
> specifically called out in the fire inspection, which will be covering
> junction boxes for the most part. How close are y'all to having a plan
> ready?
>
>
>
> Cheers
>
>
>
>
> On 2014-08-29 10:56, Steve Orth wrote:
>
> Hi,
>
> This is Steve from la Commune. I hear that Sudo was going to apply for
> some building (electrical) permits. La Commune is going to be doing the
> same. I was wondering what you all thought about the idea of us applying in
> the same bundle to possibly save cost?
>
> Im not even sure if this would save cost. But maybe it would?
>
> Hope you're both well.
>
> Thanks,
> Steve
>
>
_______________________________________________
sudo-discuss mailing list
sudo-discuss(a)lists.sudoroom.org
https://lists.sudoroom.org/listinfo/sudo-discuss
_______________________________________________
sudo-discuss mailing list
sudo-discuss(a)lists.sudoroom.org