On Wed, Aug 20, 2014 at 6:05 PM, Whitney Lawrence <whitneyel3(a)gmail.com> wrote:
I'm not making it to the meeting this evening. I
have a draft together minus
the quantity sheets, however, current q estimates are included in the shared
spreadsheet under the Qty. tab. You will notice that the estimate is $1k.
Please take a look at the pdf's and mark them up however you like and send
me red-lines I will then make v1.1 of the package with hopes of getting the
q sheet(s) done by Friday.
Whitney, sorry I just saw this now, so I don't think it got on our
meeting agenda.
You think we should be allocating $1k to electrification rather than
the $500 we agreed on last week - do I understand that right?
Additionally, I request that my August and
September dues be in the form of electrical design and installation.
We definitely encourage people to consider their labor as dues if they
are otherwise unable to pay. :)
Lastly,
because I am not a licensed electrician, these drafts need to be reviewed by
a professional prior to construction. It would suck if we had to re-run or
otherwise modify our work once the inspector comes. So if anyone has an
electrician friend that can weigh in that would be helpful. Also has anyone
put any effort into weather or not we need a permit prior to beginning this
improvement?
Once the draft is ready, I think we have two electricians in our circle so far:
* the person Jake suggested, not C10
* Dave Pedroli (gone til september)
Maybe we can ask one of them how permitting works?